How to plan penetration testing capacity.

· Makoshi team

A full calendar does not tell you whether an engagement can be delivered well. A useful capacity plan connects suitable people, real working time and all the phases the job needs.

Start with the working day.

Use the person’s actual working pattern, including breaks, part-time arrangements and non-working days. Apply employment dates and approved time away before treating time as available.

For example, 09:00–17:30 with a 30-minute unpaid break contains eight working hours. A four-hour working day contains four. Keep those differences visible when comparing availability.

Plan beyond the test window.

Separate the effort for testing, reporting, QA and any other agreed phase. Include a retest when it is within the agreed scope. Each phase needs suitable ownership and time.

Keep commercial effort and calendar reservations distinct. A quoted number of chargeable days and the actual working hours reserved for named people answer different questions.

Illustrative engagement plan — not an estimate for a particular service
PhasePlanning question
TestingWho is suitable, what access is needed and when are they available?
ReportingWhere is the time to develop and complete the report?
QAWho can review it independently, and when?
RetestIs it agreed, what is being verified and what capacity does it need?

Make unassigned work visible.

Accepted work still needs managing before it has a named tester. Keep the required roles, effort, requested window and owner visible. Otherwise, a quiet-looking staff diary can hide a growing delivery commitment.

Distinguish a request, a hold and a booking.

A request for dates is not a reservation. A hold reserves time temporarily, and a confirmed booking represents a different commitment. Give each hold an owner and an expiry when the business requires one.

When work is confirmed, convert the existing reservation. When a hold is extended, make sure its previous expiry cannot release the newer commitment.

Check three things before promising a start.

  1. Availability: suitable people have the required working time.
  2. Client confirmation: the requested dates have been agreed.
  3. Readiness: scope, access and prerequisites support an authorised start.

Keeping these separate makes an unresolved prerequisite easier to see. A free tester alone does not establish that testing can begin.

Replan the existing work.

When scope, dates or resources change, revisit the same engagement and allocations. Preserve completed work, record the change and confirm who owns any effect on client commitments.

A useful team view should help you spot the issue. A useful day view should explain the underlying hours and reservations so the next decision is informed.

How this informs Makoshi.

These principles guide our people-and-planning design. The current prototype demonstrates daily cells, hourly detail, working patterns, holds and conflicts using illustrative data. Shared operational records and production permissions remain part of the application build.